Cultural Trail update...this just in.

Southeast Corridor contractor announced

On December 8, Hunt Paving Company emerged as the lowest, most qualified bidder for the Southeast Corridor construction through the Indiana Department of Transportation's procurement process. Construction on this segment, connecting Washington St. to Fountain Square on Virginia Ave., may begin in approximately two months or by March 2011. The contractor must complete this construction by Dec. 31, 2011. Meetings will be scheduled with the contractor and adjacent neighborhoods prior to starting construction. To receive Southeast Corridor construction updates and meeting schedule please contact Gail Payne, 317.713.3333 or Gail@IndyCulturalTrail.org.